The investment intention of BHTC to build an extension to the existing plant for the assembly of electronic controls for automotive air conditioning systems
Investor: BHTC
Area of the property – 69907 m2
Built-up area Extension – 5888.92 m2
Built-up area Shed for packaging – 106.8 m2
Total built-up area Extension – 6479.96 m2
The current project includes the implementation of the production hall with a warehouse and technical premises to it.
The building is provided with accompanying facilities, such as a canopy for storing packages, expansion of the existing fire tank with another wet chamber, a transformer station and technical premises for serving the warehouse
Most part of the building is one-storey, with the exception of the mezzanine located in the northwest of the production hall at level + 5.41m, as well as technical premises which are designed on two floors
Expansion of the building is separated from the existing building by a deformation joint. The construction of the building is made of prefabricated reinforced concrete elements. The distance between the columns is 20×18 m, optimal for the production line in the production hall